Thank you all for voting on your favorite student charrette designs for Fondren's North Reading Room!
The team that received the most votes from the campus community was Team 2.
Official counts were as follows:
Team 1 120
Team 2 160
Team 3 59
Team 4 86
Fondren plans to keep all of the teams in the loop to continue seeking feedback as we move through the phases of renovating this space.
Phase 1, carpet, paint, lighting, electrical is expected to be completed October 14. We will be returning the existing reading room furniture to the space as we make plans for our next phase of new furniture and functional designs.